| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The premises shall not be occupied until the conversion work has been carried out entirely in accordance with the approved plans
The reason for the condition is:-
In order to ensure a satisfactory standard of accommodation. |
| 3. | The boundary wall and the bin store located on the Stafford Road frontage of the site shall not exceed 1.05 metres above the level of the adjacent highway carriageway and shall be retained not exceeding that height thereafter.
The reason for the condition is :-
In the interests of highway safety. |
| 4. | Prior to the commencement of any development, a flood response plan shall be submitted to and agreed in writing with the Local Planning Authority. This flood response plan shall be made available to future occupants of the site by means of a fixed notice within each individual dwelling prior to habitation.
The reason for the condition is :-
To ensure that occupants of the development are aware that the site is at risk of flooding. |
| 5. | Prior to the commencement of development, a scheme for the provision and implementation of flood proofing measures shall be submitted to and agreed, in writing, with the Local Planning Authority. The scheme shall be carried out in its entirety before the development is first occupied and constructed and completed in accordance with the approved plans and in line with the CLG publication 'Flood Resilient Construction - Improving the flood performance of new buildings'.
The reason for the condition is :-
To minimise the damage to the development in the event of flooding and enable a faster recovery once floodwaters have subsided as is set out in paragraph 5.41 of the PPS25 Practice Guide. |
| 6. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for new housing development set out in Policies HOU7 and HOU15 of the adopted Great Yarmouth Borough-wide Local Plan |