Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.Prior to the first commencement of the use hereby permitted an on-site parking and turning area shall be laid out, demarcated and retained thereafter available for that specific use. The reason for the condition is :- To ensure the provision of adequate on-site parking and turning facilities for the development.
3.NOTES - Please read the following notes carefully:-
4.The applicant's attention is drawn to the attached letter from the Environment Agency and the need to comply fully with their requirements.
5.The Environmental Health Officer has viewed the application and has made the following recommendations:- 1) Machinery, pumps, fans, etc. located in the plant room to the swimming pool are a potential source of noise nuisance. The applicant should ensure that plant is properly vibration isolated and that noise and vibration from the plant room is inaudible beyond the boundaries of the property. 2) The applicant should ensure that the proudcts of combustion from any heating system for the pool and/or the proposed building are not discharged directly into the neighbouring garden (e.g. from a horizontal flue).
6.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for domestic additions set out in Policy HOU18 of the adopted Great Yarmouth Borough-wide Local Plan.