Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the plans received by the Local Planning Authority on the 12th June 2007. The reason for the condition is: For the avoidance of doubt.
3.If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with Local Planning Authority) shall be carried out until the developer has submitted, and obtained written approval from the Local Planning Authority for, a method statement detailing how this unsuspected contamination shall be dealt with. The reason for the condition is :- To ensure that the proposed development does not cause pollution of controlled waters and that development complies with approved details in the interests of protection of Controlled Waters.
4.INFORMATIVE NOTE: The applicant's attention is drawn to the attached letter from Norfolk Fire & Rescue Service and the need to comply fully with their requirements.
5.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for alterations and extensions to buildings set out in Policy BNV18 of the adopted Great Yarmouth Borough-wide Local Plan