| No. | Condition Text |
|---|
| 1. | ----------------------------------------------------------------------- Particulars of planning permission reserving details for approval:- Application No.:-06/04/0385/O Residential Development.
Particulars of details submitted for approval:- Siting, Design,External Appearance and Landscaping. |
| 2. | The layout of the development shall be carried out in accordance with Drawing No.EA4313/02 Revision E
The Dwelling types: Drawings Nos:EA4314/03(Plot 1),EA4314/04(Plot2), EA4314/05(Plot3),EA4314/06(Plot4),EA4314/07(Plot5)EA4314/08(Plot6)REVA,EA4314/09(Plot7),EA4314/10(Plot8)EA4314/11(Plot9)EA4314/12(Plot10)EA4314/13(Plot 11) EA4314/14(Plots 13,14,15),EA4314/16(Plots 16,17) and the detail thereon.
The reason for the condition is:-
For the avoidance of doubt and to secure a properly planned development. |
| 3. | No works shall commence on the site until such time as detailed plans of the roads, footways, cycleways, foul and surface water drainage have been submitted to and agreed in writing by the Local Planning Authority in consultation with the Highway Authority.All construction works shall be carried out in accordance with the approved plans.
The reason for the condition is :-
To ensure satisfactory development of the site and a satisfactory standard of highway design and construction.
|
| 4. | No works shall be carried out on roads, footways,foul and surface water sewers otherwise than in accordance with the specifications of the Local Planning Authority in consultation with the Highway Authority.
The reason for the condition is :-
To ensure satisfactory development of the site and to ensure estate roads are constructed to a standard suitable for adoption as public highway.
|
| 5. | Before any dwelling is first occupied the roads and footways shall be constructed to Base Course surfacing level from the dwelling to the adjoining County road in accordance with the details agreed in writing with the Local Planning Authority in consultation with the Highway Authority.
The reason for the condition is :-
To ensure satisfactory development of the site.
|
| 6. | No works shall commence on site until a detailed scheme for the off-site highway works at the junction with Main Road (A1064) including improvements to the two adjacent bus stops as indicated on the approved drawing has been submitted to and approved in writing by the Local Planning Authority in consultation with the Highway Authority.
The reason for the condition is :-
To ensure that the highway improvement works are designed to an appropriate standard in the interest of highway safety and to protect the environment of the local highway corridor.
|
| 7. | Prior to the first occupation of the development hereby permitted the off-site highway improvement works referred to in Condition 6 (above) shall be completed to the written satisfaction of the Local Planning Authority in consultation with the Highway Authority.
The reason for the condition is :-
To ensure that the highway network is adequate to cater for the development proposed.
|
| 8. | None of the dwellings adjacent to the boundaries of the site shall first be occupied until details of the means of enclosure along the adjacent boundary have been submitted for the approval in writing of the Local Planning Authority and the approved details have been implemented.
The reason for the condition is :-
In the interests of the amenities of occupiers of property adjoining the application site. |
| 9. | No work shall commence until the exact type and colour of the materials to be used in the construction of the dwelling houses and hard surfaces have been submitted to and approved by the Local Planning Authority.
The reason for the condition is :-
In the interests of the visual amenities of the area as precise details of the materials have not been submitted. |
| 10. | The accomodation shown above garages on the approved plans shall only be used in association with and ancillary to the dwelling house and shall not at any time be used or sold seperately from the dwelling house.
The reason for the condition is :-
The buildings are ancillary to the dwelling house only and for the avoidance of doubt. |
| 11. | During the course of the construction hereby approved, HGV wheel washing facilities shall be provided, details of which shall be submitted to and approved by the Local Planning Authority. The approved facilities shall be retained in the agreed location until the development is completed,unless otherwise agreed in writing by the Local Planning Authority.
The reason for the condition is:-
To prevent mud and debris from being deposited on the existing road network. |
| 12. | The access for the Burgh Park residents through the site shown on the approved plans shall be retained unless otherwise agreed in writing by the local planning authority.
The reason for the condition is :-
In accordance with the approved plans. |
| 13. | The Reason for the Approval.
The application site has outline planning consent for residential development and is allocated for development in the Great Yarmouth Borough Wide Local Plan 2001. The Local Planning Authority considers that the details hereby approved subject to the above conditions and those imposed on the outline approval comply with Policy HOU5 and HOU9 of the Local Plan. |
| 14. | NOTES - Please read the following notes carefully:-
It is an OFFENCE to carry out any works within the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority This development involves work to the public highway that can only be undertaken within the scope of a legal Agreement with the applicant. Please note that it is the applicants¿ responsibility to ensure that, in addition to planning permission, any necessary Agreements under the Highways Act 1980 are also obtained. Advice on this matter can be obtained from the County Council¿s Highways Development Control Group based at County Hall in Norwich.
Public Utility apparatus may be affected by this proposal. Contact the appropriate utility service to reach agreement on any necessary alterations, which have to be carried out at the expense of the developer.
|
| 15. | Please Note:- This permission is subject to the conditions and time constraints imposed on the Outline Planning Permission 06/04/0385/O.
|