| No. | Condition Text |
|---|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The floor level of the extension shall be set no lower than existing floor levels within the building. The reason for the condition is :- In order to meet the minimum requirements of the Enviroment Agency with regard to dealing with flood risk. |
| 3. | REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the requirements of Policy EMP8 of the adopted Great Yarmouth Borough-wide Local Plan. |