| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is:-
Required to be imposed pursuant to Section 18 of the Planning (Listed Building and Conservation Areas) Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | No demolition works shall commence until a contract for the redevelopment of the site is made in accordance with the planning permission granted under Ref. No:- 06/06/0955/F or any variation of that consent or subsequent planning permission that may be granted, and details of the contract have been submitted for the agreement of the Local Planning Authority.
The reason for the condition is :-
To ensure that premature demolition does not take place to the detriment of the character and appearance of the Conservation Area. |
| 3. | No demolition works that are audible at the boundary of the site shall be carried out outside the hours of 08.00 to 17.00 on weekdays and 09.00 to 13.00 on Saturdays, nor at any time on Sundays or Bank Holidays.
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of adjacent and nearby property. |
| 4. | A supply of water, protected from frost, shall be provided for use in dust suppression.
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of adjacent and nearby property. |
| 5. | There shall be no burning of any material on site.
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of adjacent and nearby property. |
| 6. | If artificial lighting is provided, all reasonable steps shall be taken to reduce light spillage and glare. The lighting shall be switched off when the site is not occupied.
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of adjacent and nearby property.
|
| 7. | NOTES - Please read the following notes carefully:- |
| 8. | 1. In respect of condition No. 4 of this permission, physical barriers should also be provided where necessary. |
| 9. | 2. All demolition works should be carried out in accordance with the principles of British Standard 5228:1997 Noise Control on Construction and Open Sites.
|
| 10. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal satisfies the requirements of Policy BNV9 of the adopted Great Yarmouth Borough-Wide Local Plan. |