Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.No work shall commence until the exact type and colour of the facing bricks and roof tiles have been submitted to and approved by the Local Planning Authority. The reason for the condition is :- In the interests of the visual amenities of the area as precise details of these materials have not been submitted.
3.No works shall commence on site until such time as details of the slab levels of the dwellings in relation to existing/proposed ground levels have been submitted to and approved by the Local Planning Authority. The reason for the condtions is:- To ensure that the development takes place in the manner contemplated by the Local Planning Authority and to retain control over any significant changes in levels within the site.
4.Prior to the commencement of any development, a scheme for the provision and implementation of flood proofing techniques shall be submitted to, and agreed in writing with the Local Planning Authority. The works/scheme shall be carried out in their entirety before the development is first occupied, and constructed and completed in accordance with the approved plans and DCLG guidance "Preparing for Floods". The reason for the condition is :- To minimise the damage to property in the event of flooding.
5.REASON FOR APPROVAL OF THE APPLICATION :- The proposals meet the criteria for new housing development set out in Policies HOU7 and HOU15 of the adopted Great Yarmouth Borough-wide Local Plan
6.NOTES - Please read the following notes carefully:- The applicant's attention is drawn to the attached letters from Norfolk Constabulary and Norfolk Fire Service and the advice contained therein.