Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out stricty in accordance with Drawing No.652:02D and the detail thereon. The reason for the condition is :- For the avoidance of doubt.
3.The existing chalet on the site shall be demolished and all materials removed from the site prior to first occupation of the replacement dwelling hereby permitted¿ The reason for the condition is :- To esure that only one dwelling is erected on the site.
4.The development shall be constructed with a minimum finished floor level of 1.3m AODN, in accordance with the submitted Flood Risk Assessment, ref. 06252200WFR,dated 1st August 2006. The reason for the condition is :- To ensure the appropriate protection to the development/occupants and to comply with Policy INF1 of the Broads Local Plan 1997.
5.Prior to the commencent of any development, a scheme for the provision and implementation of floodproofing measures shall be submitted to and agreed in writing with the Local Planning Authority. The scheme shall be carried out in their entirety before the development is first occupied and completed in accordance with the approved plans and in accordance with ODPM guidance 'Preparing for Floods'.The recommedation of paragraph 5.3 of he submitted Flood Risk Assessment dated 1st August 2006 should as a minimum be incorporated into this scheme. The reason for the condition is :- To minimise the damage to property in the event of flooding, in accordance with the recommendations of the flood risk assessment.
6.Prior to the commencement of any development, a flood response plan shall be submitted to and agreed in writing with the Local Planning Authority. This plan, including information regarding the availability of the local flood warning system (AVM), shall be made available to future occupiers of the site by means of a fixed notice within each dwelling prior to habitation. The reason for the condition is :- To minimise the risk to the occupants in the event of flooding, in accordance with the recommendations of the flood risk assessment.
7.Prior to the commencement of development, details of the decking and perimeter of the dwelling shall be submitted to and agreed, in writing, in writing with the Local Planning Authority, in consultaion with the Environment Agency. The scheme shall incorporate void spaces that prevent the storage of materials, whilst allowing the free passage of floodwaters. The scheme shall be carried out in accordance with paragraph 4.5 of the submitted Flood Risk Assessement ref. 06252200WFR, dated 1st August 2006. The scheme shall be carried out in it's entirety before the development is first occupied. The reason for the condition is :- To prevent blockage of flood flows as a result of debris and storage and to comply with Policy INF1 of the Broads Local Plan 1997.
8.The Reason for the Approval. The local Planning Authority considers that subject to the above conditions the proposal complies with Policy INF1 and H6 of the Broads Local Plan 1997.
9.NOTES - Please read the following notes carefully:- This grant of planning permission does not grant consent for any works that may require the additional approval of the Environment Agency and the Broads Navigation Officer both parties should be contacted independent of this decision notice.