Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out strictly in accordance with the approved plans Drawings Nos.01 RevP3,02 RevP3 and 03 Rev P3, received by the Local Planning Authority on the 6 March 2007 and the detail and content thereon. The reason for the condition is :- For the avoidance of doubt and in accordance with the terms of the application.
3.Not withstanding the submitted drawings,prior to the commencement of development a full schedule of works including materials and internal and external finishes shall be submitted to and agreed in writing by the Local Planning Authority; the development shall then be carried out in accordance with the agreed details and retained in the approved condition thereafter. The reason for the condition is :- Because the precise details of materials have not been submitted as part of the application.
4.Notwithstanding the submitted plans prior to the commencement of development details of the new windows and doors (which shall be of timber construction unless otherwise agreed by the Local Planning Authority) in the form of 1-20 drawings shall be submitted to and agreed in writing by the Local Planning Authority. The reason for the condition is :- To ensure materials that are compatible with and enhance the appearance of this Grade 2 Listed Building.
5.Before any works are commenced, details of the following - for the extension- shall be submitted to and and agreed in writing, by the Local Planning Authority: -a sample of the type of brick proposed; -a sample panel of the brickwork which shall include snapped header face work - a description of the joints proposed which shall include a white cement mortar mix, profile and finish. The reason for the condition is :- To ensure that the materials and finish is appropriate to the building's status as an extension a Listed Building.
6.No part of the proposed structure shall overhang or encroach upon highway land and no door shall open outwards over the public footway. The reason for the condition is :- To prevent obstruction of the public footway in the interests of footway safety.
7.No development shall take place within the site until the applicant, or their agents or successors in title, has:- a) caused to be implemented a programme of archaelogical evaluation in accordance with a first written scheme of investigation which has been submitted to and approved in writing by the Local Planning Authority; and next b) submitted the results of the archaelogical evaluation to the Local Authority; and next c) secured the implementation of a programme of archaeological mitigatory work in accordance with a second written scheme of investigation which has been submitted to and approved in writing by the Local Planning Authority; and next, if the mitigatory work consists of a further investigation d) submitted a formal legal contract with an archaeological contractor, which has also been approved in writing by the Local Planning Authority. Such a contract will deal with all the details contained in the approved detailed second written scheme of investigation including post-excavation assessment, analysis, archiving and publication of results. The reason for the condition is :- In order to enable investigation and recording of this site of archaeological interest to take place during the period of building or engineering works.
8.The Reason for the Approval. The Local Planning Authority considers that subject to the above conditions that the the proposals comply with the aims of Policy HOU7 and BNV5 of the Great Yarmouth Borough Wide Local Plan 2001.