1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the submitted plans Drawings 123/103/C;123/104/A; and Block Plan 123/105 and the detail thereon. The reason for the condition is :- For the avoidance of doubt and in accordance with the submitted plans.
3.No part of the proposed structure shall overhang or encroach upon highway land and no door shall open outwards over the public footway. The reason for the condition is :- To prevent obstruction of the public footway in the interests of footway safety.
4.This planning approval does not grant consent for the accommodation to be used/occupied as single independent dwelling units;they shall only be occupied in assocication with the Great Yarmouth Young Persons Resettlement Scheme unless otherwise agreed in writing by the LOcal Planning Authority. The reason for the condition is :- In accordance with the terms of the application and because the size and type of accommodation is not considered suitable as general opoen market housing.
5.No development shall take place within the site until the applicant, or their agents or successors in title, has:- a) caused to be implemented a programme of archaelogical evaluation in accordance with a first written scheme of investigation which has been submitted to and approved in writing by the Local Planning Authority; and next b) submitted the results of the archaelogical evaluation to the Local Authority; and next c) secured the implementation of a programme of archaeological mitigatory work in accordance with a second written scheme of investigation which has been submitted to and approved in writing by the Local Planning Authority; and next, if the mitigatory work consists of a further investigation d) submitted a formal legal contract with an archaeological contractor, which has also been approved in writing by the Local Planning Authority. Such a contract will deal with all the details contained in the approved detailed second written scheme of investigation including post-excavation assessment, analysis, archiving and publication of results. The reason for the condition is :- In order to enable investigation and recording of this site of archaeological interest to take place during the period of building or engineering works.
6.The Reason for the Approval. The Loacl Planning Authority considers that the application complies with the aims of Policy BNV5, BNV6 and HOU23 of the Great Yarmouth Borough Wide Loacl Plan 2001.