Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with Drawing No.06/33/1 received by the local planning authority on 23 June 2006 and the detail thereon. The reason for the condition is :- For the avoidance of doubt and in accordance with the submitted application.
3.The material used in the external elevations of the extension shall match those used in the existing dwelling as closely as possible. The reason for the condition is :- As stated on the planning application form.
4.The finished floor level of the extension shall be no lower than the finished flood level of the existing dwelling and the measures to alliviate flooding as stated in the Flood Risk Assessment submitted with the application and recived by the local planning authority on the 23 June 2006, shall also be incorporated into the development. The reason for the condition is :- To implement measures to help allivate damage to the property in the event of flooding in accordance with the Flood Risk Assessment.
5.The Reason for the Approval. The local planning authority considers that subject to the above conditions, that the proposal complies with Policy H11,B11 and INF2 of the Broads Local Plan 1997.