| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the drawings received by the local planning authority on 2nd June 2006 and the detail thereon.
The reason for the condition is :-
For the avoidance of doubt and in accordance with the submitted application. |
| 3. | Prior to the commence of development,details of the materials to be used in the construction of the external roofs and walls shall be submitted to and agreed with by the local planning authority.
The reason for the condition is :-
Because the precise details have not been submitted. |
| 4. | The development shall be constructed with a minimum finished floor level of 1.19m AOD.in accordance with the submitted drawings entitled proposed extension; plans,elevations and sections,dated December 2005 and received by the local planning authority on 2nd June 2006.
The reason for the condition is :-
To ensure that the appropriate protection to the development and occupants and to comply with Policy INF2 of the Broads Local Plan 1997. |
| 5. | Prior to the commencement of development, a scheme for the provision and implementation of flood proofing techniques shall be submitted to and agreed in writing by the Local Planning Authority. The scheme shall be incorporated into the development to minimum level of 1.3m AOD and carried out in it's entirety before the devlopment is first occupied. The scheme shall be constructed and completed in accordance with the approved plan and in line with the ODPM publication'Preparing for Floods'.
The reason for the condition is :-
To minimise the damage to the development in the event of flooding and enable a faster recovery once waters have subsided.Also to comply with policy INF1 of the Broads LOcal Plan. |
| 6. | A flood evacuation plan shall be submitted and agreed, in writing with the local planning authority before occupancy of any part of the proposed development.
The reason for the condition is :-
To minimise the risk to occupants in the event of flooding and to comply with Policy INF1 of the Broads Local Plan 1997. |
| 7. | The Reason for the Approval.
The Local Planning Authority considers that the proposal complies with Policy B11,H11 and INF2 of the Broads Local Plan 1997. |
| 8. | NOTES - Please read the following notes carefully:-
a) This site comes within the Broads Internal Drainage Board whose byelaws must be complied with. In the event of of the proposed development being served by a new sewage treatment plant byelaw consent will be required and the applicant is dvised to contact the Boards Principal Engineer. |