| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | Prior to any work commencing on the site precise details of colour and design of the fencing to be installed on the site shall be submitted for the approval of the Local Planning Authority and all works shall be completed in accordance with such details as may be agreed.
The reason for the condition is :-
Precise details have not been submitted as part of the application and in the interests of the visual amenities of the locality. |
| 3. | Prior to any work commencing on the development of the site precise details of the surfacing of the site shall be submitted for the approval of the Local Planning Authority and all works in accordance with such details as may be agreed shall be completed when the works to fence the site is completed.
The reason for the condition is :-
In the interest of the visual amenities of the locality. |
| 4. | Prior to any work commencing on the development hereby permitted precise details of the treatment of the gables to be exposed by the demolition of the existing dwellings on the site together with precise detials of the front elevation of 21 St. Peters Road shall be submitted for the approval of the Local Planning Authourity and works in accordance with such details as may be agreed shall be completed concurrently with the completion of the fencing of the site.
The reason for the condition is :-
In the interests of the visual amenities of the locality. |
| 5. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal seek to enhance the area and meets overall aims of the adopted Great Yarmouth Borough-wide Local Plan. |