Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.No development shall take place until further detail of the scheme of landscaping has been submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of size, species and spacing of plants (to form the new hedges) and trees, arrangements for their protection and maintenance, and details of the proposed earthworks including the level to be formed by the soil distribution from the pond. It shall be completed within one year of the date the geothermal heating system is first brought into use and shall make provision for:- (a) re-seeding and re-planting where failures or damage occur within a period of five years from the date of planting, and (b) the replacement of any damaged or dead trees with trees of similar size and species at the next appropriate season. The reason for the condition is :- In the interests of the visual amenities of the locality. continued on next page :-
3.NOTES - Please read the following notes carefully:-
4.1. This permission does not purport to convey consent for the use of the land as residential curtilage for the adjacent barn conversion.
5.2. Attention is drawn to the contents of the attached letter from the Environment Agency.
6.REASON FOR APPROVAL OF THE APPLICATION :- The Borough Council considers that, subject to condition No. 2 of this permission, the proposal would not have a significant adverse impact on the landscape character of the area and would not, thereby, be prejudicial to the objective of Policy NNV2 of the adopted Great Yarmouth Borough-Wide Local Plan.