| No. | Condition Text |
|---|
| 1. | The development must be begun not later than 3 years beginning with the date of this permission.
The reason for the condition is:-
Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with Drawing No.1127/06/02 and the detail thereon.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | Prior to the first occupation of the development hereby permitted on-site parking area in accordance with the submitted details, together with a 400m2 servicing area, shall be provided within the curtilage of the site and shall be maintained thereafter available for that specific use.
The reason for the condition is :-
To ensure the permanent availability of the parking / manoeuvring area, in the interests of highway safety.
|
| 4. | The building hereby approved shall be used for storage only unless otherwise agreed in writing by the local planning authority.
The reason for the condition is :-
In accordance with the submitted application. |
| 5. | Prior to the commencement of any development, a scheme for the provision and implementation of pollution control to the water environment shall be submitted to and approved in writing by the local planning authority. The works/scheme shall be constructed and completed in accordance with the appoved plans/specification at such term(s) as may be specified in the approved scheme.
The reason for the condition is :-
To prevent the increased risk of pollution to the water environment. |
| 6. | The Reason for the Approval.
The proposal subject to the above conditions is consiered by the LOcal Planning Authority to comply with Policy EMP8 of the Great Yarmouth Borough Wide Local Plan 2001. |