1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with Drawing No.131/01d received by the Local Planning Authority on 20th January 2006. The reason for the condition is :- For the avoidance of doubt.
3.No work shall commence until the exact type and colour of the facing bricks and roof tiles and stone lintels have been submitted to and approved by the Local Planning Authority. The reason for the condition is :- In the interests of the visual amenities of the area as precise details of these materials have not been submitted.
4.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking and re-enacting that order) no extensions to the property shall be erected without the prior consent of the local Planning Authority. The reason for the condition is:- To enable the Local Planning Authority to retain control as the site is located in an area identified at risk of flooding by the Environment Agency.
5.The minimum finished floor level of the proposed development shall be located at or above a level of 2.20m AOD. The reason for the condition is :- To ensure that the flood risk to people and property is adequately mitigated for in accordance with PPG25.
6.The minimum finished floor level of all habitable accommodation must be set at or above a level of 3.41m AOD. The ground areas shall be limited levels to garaging storage,storage,toilets and kitchen areas. The reason for the condition is :- To ensure that the flood risk to people and property is adequately mitigated for in accordance with PPG25.
7.Floodproofing methods should be in corporated into the development to a level Prior to the commencement of any development, a scheme for the provision and implementation of floodproofing techniques to a level of 2.20m AOD shall be submitted to and agreed in writing with the Local Planning Authority. The works shall be constructed and completed in accordance with the approved plans and in accordance with ODPM guidance 'Preparing for Floods. The reason for the condition is :- To minimise the damage to property in the event of flooding in accordance with the recommendations of the flood risk assessment.
8.Prior to the commencement of development, details of construction methodology together with supporting calculations shall be submitted to and agreed in writing with the Local Planning Authority. The submitted calculations shall be sufficient to prove that the buildings will be constructed to withstand both hydrostatic and hydrodynamic pressures associated with a breach in the defence adjacent to the buildings. All buildings are to be constructed in accordance with the agreed methodology. The reason for the condition is :- To maintain the stuctural integrity of the buildings in the event of a failure of the defences.
9.Prior to the commencement of any development, a flood response plan shall be submitted to and agreed in writing with the Local Planning Authority. This plan should be made available to future occupiers of the site by means of a fixed notice within the building prior to habitation. Furthermore, a fixed sign shall be permanently displayed at the entrance to the site giving this information. All signs shall be kept legible, clear of obstruction and up to date if flood risk information changes. The reason for the condition is :- To minimise the risk to the occupants in the event of flooding.
10.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria of Policy HOU7 of the Great Yarmouth Borough-Wide Local Plan.