1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The height of the fence shall not exceed 1.6 metres above the ground level of the site. The reason for the condition is :- For the avoidance of doubt and in the interests of the visual amenities of the area.
3.No part of the proposed structure shall overhang or encroach upon the highway boundary and no gate shall open outwards over the public footway. The reason for the condition is :- To prevent obstruction of the public highway in the interests of highway safety.
4.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for domestic additions set out in Policy HOU18 of the adopted Great Yarmouth Borough-wide Local Plan.