| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The premises shall not be occupied until the conversion work has been carried out entirely in accordance with the approved plans
The reason for the condition is:-
In order to ensure a satisfactory standard of accommodation. |
| 3. | The flats shall not be occupied until works for soundproofing have been carried out in accordance with a schedule to be submitted to and approved by the Local Planning Authority in consultation with the Building Control Officer.
The reason for the condition is:-
To reduce impact and airborne noise transference between the individual flats and the adjoining properties, in the interests of the residential amenities of the occupiers of the adjoining property. |
| 4. | NOTES - Please read the following notes carefully:-
The applicants attention is drawn to the attached comments from the environmental Health Officer with respect to the proposed units of accommodation and the need to comply fully with these requirements. |
| 5. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for new the conversion of property to flats set out in Policies HOU23 and HOU24 of the adopted Great Yarmouth Borough-wide Local Plan |