| No. | Condition Text |
|---|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development hereby permitted shall, as confirmed in the agent's letter dated 11th November 2005, be carried out incorporating the flood risk mitigation measures listed as "(1)" and "(2)" in the attached "Standing Advice" note from the Environment Agency. The reason for the condition is :- To ensure that mitigation measures are undertaken as the property is located within an area at risk from flooding. |
| 3. | REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for domestic additions set out in Policy HOU18 of the adopted Great Yarmouth Borough-Wide Local Plan. continued on next page :- |