Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out including the matters (floor level and floodproofing) referred to in the agents letter dated 27th October 2005. The reason for the condition is :- For the avoidance of doubt and to ensure measures are included to minimise the risk from flooding.
3.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for domestic additions set out in Policy HOU18 of the adopted Great Yarmouth Borough-wide Local Plan.