| No. | Condition Text |
|---|
| 1. | The development must be begun not later than five years beginning with the date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990. |
| 2. | Within three months of the date of this permission, or other period that may be agreed in writing, the works set out in the attached schedule dated 1st August 2005 shall be carried out and all works shall meet the required standards and shall thereafter be maintained.
The reason for the condition is :-
To ensure a staisfactory standard of accommodation is provided. |
| 3. | Prior to the works commencement of the works referred to in condition 2 above details of the window, referred to in the attached schedule, to be installed in the ground floor flat shall be submitted to and agreed in writing with the Local Planning Authority.
The reason for the condition is :-
For the avoidance of doubt and in the interests of the visual amenities of the area. |
| 4. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for conversions set out in Policies HOU23 of the adopted Great Yarmouth Borough-wide Local Plan. |