| No. | Condition Text |
|---|
| 1. | No development whatsoever shall take place until full details of the design, external appearance, and landscaping of the development have been submitted to and approved by the Local Planning Authority and the development shall be carried out strictly in accordance with such approved details.
The reason for the condition is:-
Such details have not been submitted as part of this application. |
| 2. | Application for approval of reserved matters must be made not later than the expiration of three years beginning with the date of this permission and the development must be begun not later than whichever is the later of the following dates:- a) the expiration of five years from the date of this permission; or b) the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved.
The reason for this condition:-
Required to be imposed pursuant to Section 92 of the Town and Country Planning Act 1990. |
| 3. | The holiday accommodation shall not be occupied by any individual or family group for a period in excess of 21 days in any twelve month period.
The reason for the condition is :-
The standard of accommodation and the restricted curtilage renders the property unsuitable for permanent occupation of the number of flats to be formed. |
| 4. | The accommodation shall be used for holiday purposes only and shall not be occupied by any individual for more than 28 days at any one time without the prior written approval of the Local Planning Authority.
The reason for the condition is :-
The site is located outside any area allocated in the Broads Local Plan 1997 for permanent residential development and permanent occupation would therefore be contrary to Policy HOU H2 of the plan. |
| 5. | The development shall be constructed with a minimum finished floor level of 1.21m AODN.
The reason for the condition is :-
To ensure the appropriate protection to the development and its occupants. |
| 6. | Prior to the commencement of development, a scheme for the proviion and implementation of of flood proofing techniques shall be submitted to and agreed, in writing by the Local Planning Authority. The works shall incorporated to a level of 1.81 AODN. The works/scheme shall be carried pout in their entirety before the development is first occupied and constructed and completed in accordance with the approved plans and in accordance with the ODPM guidance @Preparing for Floods.
The reason for the condition is :-
To minimise the damage to property in the event of flooding. |
| 7. | An active flood plan shall be submitted to and agreed, in writing with the Local Planning Authority, in consultation with the Environment Agency, before occupancy of any part of the proposed development.
The reason for the condition is :-
To minimise the risk to occupants in the event of flooding. |
| 8. | Prior to the development first being occupied, the owners of the dwelling shall erect suitable permanent warning notices detailing the nature of the flood risk and the flood plan. The notices shall be submitted to and agreed, in writing, with the Local Planning Authority, in consultation with the Environment Agency. all signs shall be kept legible, clear of obstruction and up-to-date of any changes of information.
The reason for the condition is :-
To ensure the occupants of the development are aware that the site is at risk of flooding . |
| 9. | Prior to the commencement of the development hereby permitted full details (in the form of scaled plans and / or written specifications) shall be submitted to and approved in writing by the Local Planning Authority in consultation with the Highway Authority to illustrate the following:
(i) Visibility splays
(ii) Access arrangements
(iii) Parking provision in accordance with the Norfolk County Council adopted standard.
(iv) turning areas.
The reason for the condition is :-
In the interest of highway safety. |
| 10. | The Reason for the Approval.
The Local Planning Authority considers that the proposal subject to the above conditions complies with Policy H6 of the Broads Local Plan 1997. |
| 11. | NOTES - Please read the following notes carefully:-
Formal consent will be required under Schedule 10 of the Water Resources Act 1991 from the Environment Agency for a private means of effluent disposal.
Any culverts or other works affecting the flow of a watercourse will require the prior written consent of either the Repps, Martham and Thurne IDB under the terms of the Land Drainage Act 1991/Water Resources Act 1991. The IDB should be contacted in the first instance, however, if they do not wish to issue a Consent then please contact the Environment Agency. |