No.Condition Text
1.The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2.The development shall be carried out in accordance with the approved Drawings No.Plan-03 received by the Local planning Authirity on 15 March 2005. The reason for the condition is :- For the avoidance of doubt.
3.The materials used in the construction of the external walls and roofof the extension hereby approved shall match those used in the existing building in profile and colour. The reason for the condition is :- In accordance with the submitted details and to ensure the visual compatibility with the existing building.
4.The development shall be constructed with a minimum finished floor level of 3.95m AOD. The reason for the condition is :- To ensure the appropriate protection to the development and its occupants.
5.Prior to the commencement of any development, a scheme for the provision and implementation of flood proofing measures shall be submitted to and agreed, in writing by the Local Planning Authority,in consultation with the Environment Agency.The scheme hall be incorporated to aminimum level of 4.4mAOD. The works/scheme shall be carried out in its entirety before the development is first brought into use and constructed and completed in accordance with the approved plans and the ODPM guidance 'Preparing for Floods' The reason for the condition is :- To minimise the damage to property in the event of flooding.
6.Prior to the commencement of any development,a scheme for the provision and implementation of a surface water management scheme shall be submitted and agreed, in writing by the LOcal Planning Authority in consultation with the Environment Agency.The works/scheme shall then be constructed and completed before occupancy of any part of the proposed development. The reason for the condition is:- To ensure that the development does not increase the flood risk both on and off the site.
7.Prior to the development first being brought into use a flood evacuation plan specifically relating to the site shall be submitted and approved by the Local Planning Authority the plan shall be disseminated to the occupiers so they are aware of the risks associated with the site and and its location and what to do in the event of a flood. The reason for the condition is :- To protect the occupiers in the event of a flood.
8.The Reason for the Approval. The local Planning authority considers that subject to the above conditions the proposal complies with Policy EMP8 of the Great Yarmouth Borough Wide Local Plan 2001.