| No. | Condition Text |
|---|
| 1. | The development must be begun not later than five years beginning with the date of this permission.
The reason for the condition is :-
Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990. |
| 2. | No work shall commence until the exact type and colour of the materials to be used in the construction of the building hereby approved together with details of hard landscaping have been submitted to and approved in writing by the Local Planning Authority. Development shall be carried out in accordance with the approved plans.
The reason for the condition is :-
In the interests of the visual amenities of the area as precise details of the materials have not been submitted. |
| 3. | Before the development is commenced a scheme of planting and landscaping shall be submitted for the approval of the Local Planning Authority and the planting of trees and shrubs shall be carried out in accordance with the scheme as approved within three months of the approval. Any trees and shrubs so planted which dies within 5 years shall be replaced within one year by the applicants or their sucessors in title.
The reason for the condition is:-
To enhance the visual amenities of the locality |
| 4. | The development shall include the works referred to in the summary, conclusions and Appendix H of the Flood Risk Assessment prepared by MLM and received by the Local Planning Authority on the 19th April 2004 and shall thereafter be maintained in accordance with the approved details unless otherwise agreed in writing with the Local Planning Authority.
The reason for the condition is :-
To ensure measures are in place to deal with any flood that may occur in the locality.
|
| 5. | All trees other than shown to be removed on the approved plans shall be adequately protected during the period of constructionby the erection of a braced scaffold vertical and horizontal framework at least 1.2 metres high (to BS 5837) enclosed by either cleft chestnut pale fencing (to BS 1722:Part 4) or chain link fencing (to BS 1722:Part 1), which shall extend beyond either the outermost branch-spread of the tree (the drip line) or the root system whichever is the greater
The reason for the condition is :-
In order to ensure the protection of the remaining trees on the site during the construction period. |
| 6. | There shall be no raising or lowering of levels; no storage of soil, debris or building materials; and no passage of vehicles or plant within the protective barrier under any circumstances, except with the written consent and advice of the Borough Planning and Development Officer on additional protective measures.
The reason for the condition is :-
To ensure the retention of the trees on the site which are an important visual amenity in the locality. |
| 7. | NOTES - Please read the following notes carefully:-
The applicant is reminded that a Tree Preservation Order affects the site and trees marked T4, T11 and T10 on the attached drawing are protected by the Order (Note Tree T5 has been removed at some time and requires replacement which can be carried out as part of the scheme referred to above). |
| 8. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the requirements set out in the Borough-Wide Local Plan for the provision of improved health facilities. |