| No. | Condition Text |
|---|
| 1. | Application for approval of reserved matters must be made not later than the expiration of three years beginning with the date of this permission and the development must be begun not later than whichever is the later of the following dates:- a) the expiration of five years from the date of this permission; or b) the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved.
The reason for this condition:-
Required to be imposed pursuant to Section 92 of the Town and Country Planning Act 1990. |
| 2. | No development whatsoever shall take place until full details of the siting, design, external appearance and landscaping of the development have been submitted to and approved by the Local Planning Authority and the development shall be carried out strictly in accordance with such approved details.
The reason for the condition is:-
Such details have not been submitted as part of this application. |
| 3. | The access to and within the site shall be in accordance with Drawing No. 0871.05 Rev A incorporating a 2 metre x site extremity visibility splay and minimum 1.8m wide footpath shall be provided along the western site frontage to adjoin the existing footway on the realigned section of Hall Road.The footway and visibility splay shall be provided prior to the dwellings first being occupied and no structure, obstacle or planting above 0.6 metre high shall be erected or grown within the visibility splay.The existing pedestrian bollards shall be repositioned to the north of the access to Plots 1 and 2 on the the indictive layout plan.
The reason for the condition is:-
In accordance with the submitted details and in the interests of highway safety. |
| 4. | Prior to commencement of the development and to the satisfaction of the Head of Environmental Health, a site investigation shall be carried out to assess whether the land is contaminated.The investigation shall include details of previous uses and possible contamination arising from those uses.If contamination is found or suspected to exist,a scheme to remediate the site to a standard suitable for its proposed use shall be submitted to and approved by the Local Planning Authority in conjunction with the Head of Environmental Health.
The reason for the condition is:-
To ensure that the site is free of contamination for the protection of the future occupiers of the site in accordance with the Environmental Protection Act 1990. |
| 5. | Prior to the first occupation of the dwellings hereby approved a new pedestrian footway, designed and constructed in accordance with Norfolk County Council approved footway specification and to include full upstand kerbing, shall be provided adjacent to Hemsby Road at the access to Plot 1 on the indicative layout plan.
The reason for the condition is:-
In the interests of highway safety and to provide a footway to adoptable standard. |
| 6. | Prior the first occupation of the development hereby permitted the vehicular access shall be constructed in accordance with the Norfolk County Council residential construction specification ,and additionally to accord with details to be approved in writing by the Local planning Authority in conjunction with the highway authority.
The reason for the condition is:-
To ensure satisfactory access into the site. |
| 7. | The access shall be constructed with adequate drainage measures to prevent surface water run-off onto the adjacent public highway, in accordance with a detailed scheme submitted to and approved in writing by the Local Planning Authority,in consultaion with the Highway
Authority.
The reason for the condition is:-
To prevent extraneous material being deposited on the highway. |
| 8. | Details of foul and surface water drainage in connection with the development shall be submitted to and approved by the Local Planning Authority before any works on the site commences. The drainage shall constructed in accordance with the approved details.
The reason for the condition is:-
To ensure satisfactory drainage of the site. |
| 9. | All existing hedgerows on the boundaries of the site shall be retained unless otherwise agreed in writing by the Local Planning Authority;and the hedges shall be protected during the constructuction process by a means to be agreed with the Local planning Authority prior to the development commencing
To retain the visual amenity afforded by the natural features and to enhance the appearance of the development. |