1.The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2.The development shall be carried out in accordance with Drawings Nos.3947/A/10A, 3972/SPRE/4,3972/PRE5,6 and 7,3972/PRE/8B, /9B, /10A, /11sA,/3A,/4B,/5 and 3994/PRE/3A,/4B and/5 and 3990/A/1B,3990/A/2:- thesiting of the temporary portacabins shall be in accordance with Drawings No.4000/A/2 and 4000/A/2. The reason for the condition is:- For the avoidance of doubt and in accordance with the submitted details.
3.No work shall commence until the exact type and colour of the facing bricks, cladding and roof tiles have been submitted to and approved by the Local Planning Authority. The reason for the condition is :- In the interests of the visual amenities of the area as precise details of these materials have not been submitted.
4.The development shall not be brought into use until such time as the car parking shown on the approved plans has been provided unless otherwise agreed in writing by the Local Planning Authority. The reason for the condition is:- To ensure the provision of satisfactory on site parking provision.
5.Should the number of pupils attending the college at the date of this permission be exceeded by 10% on a permanant basis as a result of the development hereby approved, a scheme for the funding and enhancement of pedestrian/cycle facilities at the signal junction at Church Lane/Magalen Way/Crab Lane/Shrublands Way shall be submitted to and agreed in writing by the Local Planning Authority in conjunction with the Highway Authority. The reason for the condition is:- Because the Traffic Assessment submitted with the application identifies the need for enhanced pedestrian facilities.
6.Notwithstanding the submitted plans prior to the commencement of development, a 1:100 plan for the revised car park access- which shall show the relationship of the access to the bus stop on Church Road and shall include the visibility splays- shall be submitted to and agreed in writing by the Local Planning Authority.The scheme shall then be carried out in accordance with the approved details and made available for use before the complex is commissioned or any other such time agreed by the Local Planning Authority. The reason for the condition is:- In the interests of highway safety.