| No. | Condition Text |
|---|---|
| 1. | The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990. |
| 2. | No work shall commence until the exact type and colour of the exterior cladding have been submitted to and approved by the Local Planning Authority. The reason for the condition is :- In the interests of the visual amenities of the area as precise details of the materials have not been submitted. |
| 3. | The premises hereby permitted shall only be used in conjunction with the adjoining industrial unit and shall not be used as a separate industrial unit. The reason for the condition ia:- To ensure the use of the premises takes place in the manner contemplated by the Local Planning Authority on the grant of this permission. |