Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than five years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2.The development hereby permitted shall be carried out in accordance with Drawing Nos. 890-01B and 890-02. The reason for the condition is :- To ensure the permission relates to the correct documents.
3.No development shall take place until details of the exact type and colour of the facing bricks and roof tiles to be used in the construction of the toilet/shower block have been submitted to and approved in writing by the Local Planning Authority. The reason for the condition is :- In the interests of the visual amenities of the locality as precise details of these materials have not been submitted. continued on next page :-
4.No development shall take place until further detail of the scheme of landscaping indicated on Drawing No. 890-01B has been submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of numbers, size, species and spacing of plants, and arrangements for their protection and maintenance. It shall be carried out in the first planting season following the touring caravan site first being brought into use and shall make provision for re-planting where failures or damage occur within a period of five years from the date of planting. The reason for the condition is :- In the interests of the visual amenities of the locality.
5.No development shall take place until details of the construction of the car parking areas for the clubhouse and entertainers have been submitted to and approved in writing by the Local Planning Authority; and the touring caravan site shall not be brought into use until these areas have been constructed in accordance with the approved details and demarcated as indicated on Drawing No. 890-01B. The reason for the condition is :- To ensure that adequate parking facilities are provided.
6.The touring caravan site shall not be brought into use until the proposed access road has been constructed in accordance with the details indicated on Drawing No. 890-01B. The reason for the condition is :- To ensure that an adequate means of access is provided.
7.The loading/unloading area indicated on Drawing No. 890-01B shall be kept free of obstruction and available for that purpose at all times. The reason for the condition is :- To enable the clubhouse to be adequately serviced.
8.The touring caravan site shall operate during the period from 1st March to 31st October only in any year. The reason for the condition is :- To ensure that the site is not used for permanent residential purposes contrary to the provisions of the Modified Deposit Version of the Borough-Wide Local Plan.